Series: ASM Failure Analysis Case Histories
Publisher: ASM International
Published: 01 June 2019
DOI: 10.31399/asm.fach.process.c0047176
EISBN: 978-1-62708-235-8
... to detect overheating. The clamps in stock should be inspected to ensure that the metal had not been weakened by overheating during the upset forging operation. Clamps Forgings Overheating 8740 AMS 6322 UNS G87400 Metalworking-related failures Brittle fracture The ring clamp shown in Fig...
Series: ASM Failure Analysis Case Histories
Volume: 1
Publisher: ASM International
Published: 01 December 1992
DOI: 10.31399/asm.fach.v01.c9001093
EISBN: 978-1-62708-214-3
... following hot heading and prior to the production run. The process chart for hot heading was changed from water quenching to air cooling following the forming operation. Water quenching 8740 UNS G87400 Heat treating-related failures Intergranular fracture Background A heat-treated, cadmium...
Series: ASM Failure Analysis Case Histories
Publisher: ASM International
Published: 01 June 2019
DOI: 10.31399/asm.fach.mech.c0048634
EISBN: 978-1-62708-225-9
... from the pins, which were then baked and repeated with a dull, porous cadmium layer that allowed outward diffusion of hydrogen. The pins were baked again after deposition of the porous cadmium layer. This eliminated the problem. Electroplating Fasteners Hydrogen embrittlement 8740 UNS G87400...
Series: ASM Failure Analysis Case Histories
Volume: 2
Publisher: ASM International
Published: 01 December 1993
DOI: 10.31399/asm.fach.v02.c9001379
EISBN: 978-1-62708-215-0
... 8740 UNS G87400 Heat treating-related failures Hydrogen damage and embrittlement Background The heads of two bolts severed while being installed into an Army tank recoil mechanism. Applications Twelve bolts (4.13-in.) secure the recoil mechanism which absorbs the high impact forces...